Schedule updating process


31-Jul-2020 23:35

Typically, correcting OOS logic for driving activities on the Critical Path will shorten the Remaining Duration of the Project Schedule.

Please see the previous post, Schedule Performance Measurement, Part 3. I then check for changes to Activity and Relationship Calendars and Calendar assignments.For example, if activity A drives activity B with an FS Relationship and Activity A is assigned an Actual Start Date with a projected scheduled Finish Date and activity B is assigned an Actual Start Date, activity A will show up on the Schedule Log as having OOS Logic because activity A does not have an Actual Finish Date prior to activity B actually starting. If activity A has not actually started and activity B is assigned an Actual Start Date, then more work must be done to correct the OOS logic.



making your telescope setup much easier and more precise!… continue reading »


Read more